During the most recent month at Luinstra Corporation, queue timewas 4.5 days, inspection time was 0.8 day, process time was 1.9days, wait time was 5.1 days, and move time was 0.7 day.
Required:
a. Compute the throughput time.
b. Compute the manufacturing cycle efficiency (MCE).
c. What percentage of the production time is spent innon-value-added activities?
d. Compute the delivery cycle time.
During the most recent month at Luinstra Corporation, queue timewas 4.5 days, inspection time was 0.8 day, process time was 1.9days, wait time was 5.1 days, and move time was 0.7 day.
Required:
a. Compute the throughput time.
b. Compute the manufacturing cycle efficiency (MCE).
c. What percentage of the production time is spent innon-value-added activities?
d. Compute the delivery cycle time.