Jaster Corporation's management keeps track of the time it takesto process orders. During the most recent month, the followingaverage times were recorded per order:
Days Wait time 11.7 Inspection time 0.5 Process time 1.20 Move time 0.2 Queue time 2.4
Required: a. Compute the throughput time.(Round your answer to 2decimal places.)
Throughput time days
b. Compute the manufacturing cycle efficiency (MCE). (Donot round intermediate calculations. Round your answer to nearestwhole percentage. Omit the "%" sign in your response.)
MCE %
c. What percentage of the production time is spent innon-value-added activities? (Do not round intermediatecalculations. Round your answer to nearest whole percentage. Omitthe "%" sign in your response.)
Percentage of theproduction time %
d. Compute the delivery cycle time. (Round your answer to 1decimal place.)
Delivery cycletime days
Jaster Corporation's management keeps track of the time it takesto process orders. During the most recent month, the followingaverage times were recorded per order: |
Days | |
Wait time | 11.7 |
Inspection time | 0.5 |
Process time | 1.20 |
Move time | 0.2 |
Queue time | 2.4 |
Required: | |
a. | Compute the throughput time.(Round your answer to 2decimal places.) |
Throughput time | days |
b. | Compute the manufacturing cycle efficiency (MCE). (Donot round intermediate calculations. Round your answer to nearestwhole percentage. Omit the "%" sign in your response.) |
MCE | % |
c. | What percentage of the production time is spent innon-value-added activities? (Do not round intermediatecalculations. Round your answer to nearest whole percentage. Omitthe "%" sign in your response.) |
Percentage of theproduction time | % |
d. | Compute the delivery cycle time. (Round your answer to 1decimal place.) |
Delivery cycletime | days |