Inspection time 0.2 days Wait time (from order to start of production) 17.1 days Process time 3.5 days Move time 0.9 days Queue time 3.8 days
Requirement 1: Compute the throughput time. (Round your answer to 1 decimal place.)
Throughput time days
Requirement2: Compute the manufacturing cycle efficiency (MCE) for thequarter. (Round your answer to 2 decimal place.) Manufacturing cycle efficiency
Requirement 3: What percentage of the throughput time was spent in non-value-addedactivities? (Round your answer to the nearest whole number.)
Throughput time %
Requirement 4: Compute the delivery cycle time.(Roundyour answer to 1 decimal place.)
Delivery cycle time days
Requirement 5: If by using Lean Production all queue time during production iseliminated, what will be the new MCE?(Roundyour answer to 3 decimal places.)
Manufacturing cycle efficiency
Inspection time | 0.2 | days |
Wait time (from order to start of production) | 17.1 | days |
Process time | 3.5 | days |
Move time | 0.9 | days |
Queue time | 3.8 | days |
Requirement 1: |
Compute the throughput time. (Round your answer to 1 decimal place.) |
Throughput time | days |
Manufacturing cycle efficiency | |
Requirement 3: |
What percentage of the throughput time was spent in non-value-addedactivities? (Round your answer to the nearest whole number.) |
Throughput time | % |
Requirement 4: |
Compute the delivery cycle time.(Roundyour answer to 1 decimal place.) |
Delivery cycle time | days |
Requirement 5: |
If by using Lean Production all queue time during production iseliminated, what will be the new MCE?(Roundyour answer to 3 decimal places.) |
Manufacturing cycle efficiency |