On May 1st, the PM sent a memo to their boss stating that Project X would require 13 weeks to complete (see network logic below – activity on node diagraming) at a total project cost of $62K.

 

 

 

HW3 P5 Network

 

 

 

Unknown to the PM, there was a contract executed whereby it was was agreed that there would be a $5K penalty payment per week for every week the project exceeds six (6) weeks.

 

 

 

As such, the PM developed the following costing (all costs are in K’s) and timing matrix (all timings are in weeks).

 

 

 

Normal

 

 

 

Crash

 

Activity

 

Time

 

Cost

 

 

 

Time

 

Cost

 

Additional Cost per Week

 

A

 

3

 

$6

 

 

 

2

 

$8

 

$2

 

B

 

5

 

$12

 

 

 

4

 

$13.5

 

$1.5

 

C

 

5

 

$16

 

 

 

3

 

$22

 

$3

 

D

 

4

 

$8

 

 

 

2

 

$10

 

$1

 

E

 

2

 

$6

 

 

 

1

 

$7.5

 

$1.5

 

F

 

3

 

$14

 

 

 

1

 

$20

 

$3

 

 

 

Total

 

$62

 

 

 

 

 

 

 

 

 

 

 

What is the minimum amount of additional funding (beyond the project budget of $62K) the PM should request (given the contractual penalty provision)?

For unlimited access to Homework Help, a Homework+ subscription is required.

Unlock all answers

Get 1 free homework help answer.
Already have an account? Log in
Already have an account? Log in
Already have an account? Log in
Already have an account? Log in
Already have an account? Log in
Avatar image
Read by 1 person
Already have an account? Log in
Avatar image
Read by 2 people
Already have an account? Log in

Related questions

Weekly leaderboard

Start filling in the gaps now
Log in