Nanner Corporation is trying to determine how long it takes for oneproduct to pass through the production process. The followinginformation was gathered regarding how many days the product spentin various production activities:
Activity................Number of Days
Inspection............5
Nanner Corporation is trying to determine how long it takes for oneproduct to pass through the production process. The followinginformation was gathered regarding how many days the product spentin various production activities:
Activity................Number of Days
Inspection............5
2
answers
0
watching
56
views
For unlimited access to Homework Help, a Homework+ subscription is required.
15 Jul 2022
Unlock all answers
Get 1 free homework help answer.
Already have an account? Log in
Elin HesselLv2
11 Aug 2019
Get unlimited access
Already have an account? Log in
Related questions
Nanner Corporation is trying to determine how long it takes for oneproduct to pass through the production process. The followinginformation was gathered regarding how many days the product spentin various production activities: |
Activity | Number of Days |
Inspection | 5 |
Storage | 6 |
Assembly | 4 |
Handling | 2 |
Painting | 1 |
Packaging | 1 |
a. | Which of the above activities are value-added? |
|
b. | What is Nanner's total cycle time? |
Total cycle | days |
c. | Determine Nanner's manufacturing efficiency ratio. (Round your answer to2 decimal places. Omit the "%" sign in yourresponse.) |
Manufacturing efficiency ratio | % |
d. | If Nanner implements a total quality management program and ajust-in-time inventory system. What would be the change in Nanner'smanufacturing efficiency ratio? (Round your answer to2 decimal places. Omit the "%" sign in yourresponse.) |
Manufacturing efficiency ratio | % |