Nanner Corporation is trying to determine how long it takes for oneproduct to pass through the production process. The followinginformation was gathered regarding how many days the product spentin various production activities:
Activity Number of Days Inspection 5 Storage 6 Assembly 4 Handling 2 Painting 1 Packaging 1
a. Which of the above activities are value-added?
Assembly and painting Handling and packaging Inspection and storage
b. What is Nanner's total cycle time?
Total cycle days
c. Determine Nanner's manufacturing efficiency ratio. (Round your answer to2 decimal places. Omit the "%" sign in yourresponse.)
Manufacturing efficiency ratio %
d. If Nanner implements a total quality management program and ajust-in-time inventory system. What would be the change in Nanner'smanufacturing efficiency ratio? (Round your answer to2 decimal places. Omit the "%" sign in yourresponse.)
Manufacturing efficiency ratio %
Nanner Corporation is trying to determine how long it takes for oneproduct to pass through the production process. The followinginformation was gathered regarding how many days the product spentin various production activities: |
Activity | Number of Days |
Inspection | 5 |
Storage | 6 |
Assembly | 4 |
Handling | 2 |
Painting | 1 |
Packaging | 1 |
a. | Which of the above activities are value-added? |
|
b. | What is Nanner's total cycle time? |
Total cycle | days |
c. | Determine Nanner's manufacturing efficiency ratio. (Round your answer to2 decimal places. Omit the "%" sign in yourresponse.) |
Manufacturing efficiency ratio | % |
d. | If Nanner implements a total quality management program and ajust-in-time inventory system. What would be the change in Nanner'smanufacturing efficiency ratio? (Round your answer to2 decimal places. Omit the "%" sign in yourresponse.) |
Manufacturing efficiency ratio | % |