Two-Stage ABC for Manufacturing
Detroit Foundry, a large manufacturer of heavy equipmentcomponents, has determined the following activity cost pools andcost driver levels for the year:

Activity Cost Pool Activity Cost

Activity Cost Driver

Machine setup $672,000

12,000 setup hours

Material handling 192,000

2,000 materialmoves

Machine operation 500,000

10,000 machine hours

The following data are for the production of single batches oftwo products, C23 Cams and U2 Shafts during the month ofAugust:

C23 Cams U2 Shafts
Units produced 500 300
Machine hours 4 5
Direct labor hours 200 400
Direct labor cost $11,000 $16,000
Direct materials cost $36,000 $26,000
Tons of materials 13 8
Setup hours 3 7

Determine the unit costs of C23 Cams and U2 Shafts usingABC.
Round cost per gallon to two decimal places.

Product Costs
C23 Cams U2 Shafts
Direct materials $Answer $Answer
Direct labor Answer Answer
Manufacturing overhead:
Machine setups Answer Answer
Material handling Answer Answer
Machine operation Answer Answer
Total job costs $Answer $Answer
Units produced Answer Answer
Cost per unit produced $Answer $Answer

For unlimited access to Homework Help, a Homework+ subscription is required.

Casey Durgan
Casey DurganLv2
28 Sep 2019

Unlock all answers

Get 1 free homework help answer.
Already have an account? Log in

Related questions

Weekly leaderboard

Start filling in the gaps now
Log in