1
answer
0
watching
279
views
24 Sep 2018
A company considers a new project. The required rate of return (WACC) on the project is 10 percent. Which of the following statement is correct?
A. If the projectâs NPV = $1,500, the company should accept the project.
B. If the projectâs IRR < 10 percent, the company should accept the project.
C. If the projectâs MIRR < 10 percent, the company should accept the project.
D. If the projectâs PI > 0, the company should accept the project.
E. If the projectâs payback period > required cutoff payback, the company should accept the project.
F. If the projectâs NPV < 0 and IRR > 10 percent, the company should accept the project.
A company considers a new project. The required rate of return (WACC) on the project is 10 percent. Which of the following statement is correct?
A. If the projectâs NPV = $1,500, the company should accept the project.
B. If the projectâs IRR < 10 percent, the company should accept the project.
C. If the projectâs MIRR < 10 percent, the company should accept the project.
D. If the projectâs PI > 0, the company should accept the project.
E. If the projectâs payback period > required cutoff payback, the company should accept the project.
F. If the projectâs NPV < 0 and IRR > 10 percent, the company should accept the project.
Nestor RutherfordLv2
25 Sep 2018