1
answer
0
watching
341
views
tantiger854Lv1
29 Sep 2019
Question: The Sanders Electric Company is evaluating two projects for possible inclusion in the firmâs capital budget. Project M will require a $37,000 investment while project Oâs investment will be $46,000. After-tax cash inflows are estimated as follows for the two projects: Year Project M Project O 1 $12,000 $10,000 2 12000 10000 3 12000 15000 4 12000 15000 5 15000 a. Determine the payback period for each project. Payback (M) = Payback (O) = b. Calculate the net present value and profitability index for each project based on a 10 percent cost of capital. Which, if either, of the project is acceptable? NPV (M) = PI (M) = NPV (O) = PI (O) = c. Determine the internal rate of return and modified internal rate of return for Projects M and O. IRR (M): IRR (O): MIRR calculation of project M: MIRR calculation of project O:
Question: | ||||
The Sanders Electric Company is evaluating two projects for possible inclusion in the firmâs capital budget. Project M will require a $37,000 investment while project Oâs investment will be $46,000. After-tax cash inflows are estimated as follows for the two projects: | ||||
Year | Project M | Project O | ||
1 | $12,000 | $10,000 | ||
2 | 12000 | 10000 | ||
3 | 12000 | 15000 | ||
4 | 12000 | 15000 | ||
5 | 15000 | |||
a. | Determine the payback period for each project. | |||
Payback (M) = | ||||
Payback (O) = | ||||
b. | Calculate the net present value and profitability index for each project based on a 10 percent cost of capital. Which, if either, of the project is acceptable? | |||
NPV (M) = | ||||
PI (M) = | ||||
NPV (O) = | ||||
PI (O) = | ||||
c. | Determine the internal rate of return and modified internal rate of return for Projects M and O. | |||
IRR (M): | ||||
IRR (O): | ||||
MIRR calculation of project M: | ||||
MIRR calculation of project O: |
Nestor RutherfordLv2
29 Sep 2019