A manufacturer of skis produces two types: downhill and cross-country. The times required for manufacturing and finishing each ski are given in the following table.
--
Downhill | Cross-Country
Manufacturing time per ski--- 2 hours | 1.5 hours
Finishing time per ski------------1 hour | 1.5 hours
--
The maximum total weekly hours available for manufacturing and finishing the skis are 84 hours and 60 hours, respectively. The profits per ski are $40 for Downhill and $90 for cross-country. Determine how many of each kind of ski should be produced to achieve a maximum profit.
How man of each kind of ski should be produced to achieve maximum profit?
The manufacturer should produce____downhill skis and ____cross-country skis.
A manufacturer of skis produces two types: downhill and cross-country. The times required for manufacturing and finishing each ski are given in the following table.
--
Downhill | Cross-Country
Manufacturing time per ski--- 2 hours | 1.5 hours
Finishing time per ski------------1 hour | 1.5 hours
--
The maximum total weekly hours available for manufacturing and finishing the skis are 84 hours and 60 hours, respectively. The profits per ski are $40 for Downhill and $90 for cross-country. Determine how many of each kind of ski should be produced to achieve a maximum profit.
How man of each kind of ski should be produced to achieve maximum profit?
The manufacturer should produce____downhill skis and ____cross-country skis.