1
answer
0
watching
265
views
6 Aug 2018

Looking to achieve the highest grade possible, please see below. Please indicate if this answer is correct. IF I have left a calcuation out, please include.

Thank you,

The Big Bus Company manufactures two products, Product 1 and Product 2. Product 2 was developed as an attempt to enter a market closely related to that of Product 1. Product 2 is the more complex of the two products, requiring three hours of direct labour time per unit to manufacture compared to one and one-half hours of direct labour time for Product 1. Product 2 is produced on an automated production line.

Overhead is currently assigned to the products on the basis of direct labour-hours. The company estimated it would incur a total of $396,000 in manufacturing overhead costs and produce 5,500 units of Product 2 and 22,000 units of Product 1 during the current year. Unit costs for materials and direct labour are:
Product 1 Product 2
Direct Labour $7 $15
Direct material $9 $20
Required:
a. Compute the predetermined overhead rate under the current method of allocation and determine the unit product cost of each product for the current year. (5 marks)
Product 1 Product 2 Total Allocation
Direct Labour hour / unit 1.5 3 396,000 / 49,500
units produced 22,000 5,500 8
total labour hour 33,000 16,500 49,500
overhead/unit 12 24 overhead/unit is calculated by direct LH x 8
Product 1 Product 2
Direct material 9 20
Direct labour 7 15
overhead/unit 16 35
cost/unit 32 70
b. The company's overhead costs can be attributed to four major activities. These activities and the amount of overhead cost attributable to each for the current year are given below: (5 marks)
Expected Activity
Activity Costs Pools Estimated Overhead Costs Product 1 Product 2 Total
Machine set-ups required $170,000 700 1,000 1,700
Purchase orders issued 37,000 300 200 500
Machine-hours required 91,000 4,000 9,000 13,000
Maintenance requests issued 98,000 400 600 1,000
$396,000
Using the data above and an activity-based costing approach, determine the unit product cost of each product for the current year.
Total Cost Product A Product B
Machine Setups 170,000 70,000 100,000
purchase order 37,000 22,200 14,800
machine hours 91,000 28,000 63,000
maintenance requests 98,000 39,200 58,800
Total 396,000 159,400 236,600
22,000 5,500
overhead /cost 7..25 43..02
product 1 product 2
Direct Labour 9 20
direct material 7 15
overhead / unit 7..25 43.02.
Unit/ cost 23..25 78.020.

For unlimited access to Homework Help, a Homework+ subscription is required.

Jarrod Robel
Jarrod RobelLv2
8 Aug 2018

Unlock all answers

Get 1 free homework help answer.
Already have an account? Log in

Related questions

Related Documents

Weekly leaderboard

Start filling in the gaps now
Log in