Problem 5A-8 High-Low Method; Predicting Cost [LO5-10]

Nova Company’s total overhead cost at various levels of activityare presented below:

Month Machine-
Hours
Total
Overhead
Cost
April 51,000 $ 181,360
May 41,000 $ 157,760
June 61,000 $ 204,960
July 71,000 $ 228,560

Assume that the total overhead cost above consists of utilities,supervisory salaries, and maintenance. The breakdown of these costsat the 41,000 machine-hour level of activity is:

Utilities (variable) $ 53,300
Supervisory salaries(fixed) 48,000
Maintenance (mixed) 56,460
Total overhead cost $ 157,760

Nova Company’s management wants to break down the maintenancecost into its variable and fixed cost elements.

Required:

1. Estimate how much of the $228,560 of overhead cost in Julywas maintenance cost. (Hint: to do this, it may be helpfulto first determine how much of the $228,560 consisted of utilitiesand supervisory salaries. Think about the behavior of variable andfixed costs.)

2. Using the high-low method, estimate a cost formula formaintenance in the form Y = a + bX.

3. Express the company’s total overhead cost in theform Y = a + bX.

4. What total overhead cost would you expect to beincurred at an activity level of 46,000 machine-hours?

For unlimited access to Homework Help, a Homework+ subscription is required.

Beverley Smith
Beverley SmithLv2
5 Dec 2018

Unlock all answers

Get 1 free homework help answer.
Already have an account? Log in

Related questions

Related Documents

Weekly leaderboard

Start filling in the gaps now
Log in