Which best describes the difference between general and job overhead costs?

a. General overhead costs that are incurred regardless of whether a project is being executed. These are the costs associated with operating the construction company. Conversely, job overhead is the administrative costs directly associated with the execution of a specific project.

b. General overhead costs that are incurred after a project is being executed, job overhead is the administrative costs directly associated with the execution of a specific project. These are the costs associated with operating the construction company.

c. General overhead costs that are incurred regardless of whether a project is being executed. These are the costs associated with operating the owner's new facility. Conversely, job overhead is the administrative costs directly associated with the execution of a specific project.

d. None of these.

 

For unlimited access to Homework Help, a Homework+ subscription is required.

Unlock all answers

Get 1 free homework help answer.
Already have an account? Log in
Already have an account? Log in
Joshua Stredder
Joshua StredderLv10
12 Jan 2021
Already have an account? Log in

Related questions

Weekly leaderboard

Start filling in the gaps now
Log in