The primary difference between a static budget and a flexible budget is that a static budget
a. The static budget contains only fixed costs, while the flexible budget contains only variable costs.
b. The static budget is prepared for a single level of activity, while a flexible budget is adjusted for different activity levels.
c. The flexible budget is prepared for a single level of activity, while a static budget is adjusted for different activity levels.
d. The static budget is constructed using input from only upper-level management, while a flexible budget obtains input from all levels of management.
e. The flexible budget is constructed using input from only upper-level management, while a static budget obtains input from all levels of management.
The primary difference between a static budget and a flexible budget is that a static budget
a. The static budget contains only fixed costs, while the flexible budget contains only variable costs.
b. The static budget is prepared for a single level of activity, while a flexible budget is adjusted for different activity levels.
c. The flexible budget is prepared for a single level of activity, while a static budget is adjusted for different activity levels.
d. The static budget is constructed using input from only upper-level management, while a flexible budget obtains input from all levels of management.
e. The flexible budget is constructed using input from only upper-level management, while a static budget obtains input from all levels of management.