Smith produces specialized equipment..Currently the company usestradtional sytem for allocating manufacturing overhead. Overheadcosts are allocated at a rate of 5 dollars per machoine hours lastyear. Smiths CEO has heard about activity based costing and wantsto try out.

Cost Pool AMount Cost Price

Setups 30,0000 Number of setups

Equiptment 20,000 Machine hours

Inspection 50,000 Inspections

Company estimated it will perform 150 setups and 1000inspections each year and 20,000 machine hours each year

A job FWS will require 18 setups 85 machine hours and 60inspections. What amount of manufacturing Overhead will beallocated using job FWS?

What is the total cost of the job if direct material is 200 anddirect labor is 150?

What amount of manufacturing overhad would SMmith allocate tojob FWs using their traditional system?

What is the total cost if direct material is 200 and direct laoris 150?

For unlimited access to Homework Help, a Homework+ subscription is required.

Patrina Schowalter
Patrina SchowalterLv2
28 Sep 2019

Unlock all answers

Get 1 free homework help answer.
Already have an account? Log in

Related questions

Weekly leaderboard

Start filling in the gaps now
Log in