On March 1, 2012, Newton Company purchased land for an officesite by paying $900,000 cash. Newton began construction on theoffice building on March 1. The following expenditures wereincurred for construction: Date Expenditures March 1, 2012 $ 600,000 April 1, 2012 840,000 May 1, 2012 1,500,000 June 1, 2012 2,400,000
The office was completed and ready for occupancy on July 1. Tohelp pay for construction, $1,200,000 was borrowed on March 1, 2012on a 9%, 3-year note payable. Other than the construction note, theonly debt outstanding during 2012 was a $500,000, 12%, 6-year notepayable dated January 1, 2012.
78. The weighted-average accumulated expenditures on theconstruction project during 2012 were a. $640,000. b. $4,890,000. c. $520,000. d. $1,160,000.
79. The actual interest cost incurred during 2012 was a. $150,000. b. $168,000. c. $84,000. d. $140,000.
80. Assume the weighted-average accumulated expenditures forthe construction project are $870,000. The amount of interest costto be capitalized during 2012 is a. $130,500. b. $138,000. c. $150,000. d. $168,000.
Use the following information for questions 78 through80.
On March 1, 2012, Newton Company purchased land for an officesite by paying $900,000 cash. Newton began construction on theoffice building on March 1. The following expenditures wereincurred for construction:
Date Expenditures
March 1, 2012 $ 600,000
April 1, 2012 840,000
May 1, 2012 1,500,000
June 1, 2012 2,400,000
The office was completed and ready for occupancy on July 1. Tohelp pay for construction, $1,200,000 was borrowed on March 1, 2012on a 9%, 3-year note payable. Other than the construction note, theonly debt outstanding during 2012 was a $500,000, 12%, 6-year notepayable dated January 1, 2012.
78. The weighted-average accumulated expenditures on theconstruction project during 2012 were
a. $640,000.
b. $4,890,000.
c. $520,000.
d. $1,160,000.
79. The actual interest cost incurred during 2012 was
a. $150,000.
b. $168,000.
c. $84,000.
d. $140,000.
80. Assume the weighted-average accumulated expenditures forthe construction project are $870,000. The amount of interest costto be capitalized during 2012 is
a. $130,500.
b. $138,000.
c. $150,000.
d. $168,000.