If a company has computed a project profitability index of-0.015 for an investment project, then:

a the project's internal rate of return is greater than thediscount rate.
b the relationship of the internal rate of return and thediscount rate is impossible to determine from the data given.
c the project's internal rate of return is less than the discountrate.
d the project's internal rate of return is equal to the discountrate.