Waltner Corporation's management reports that its averagedelivery cycle time is 20.0 days, its average throughput time is13.5 days, its manufacturing cycle efficiency (MCE) is 0.44, itsaverage move time is 0.2 day, and its average queue time is 4.0days.
Required: a. What is the wait time? (Round your answer to 1 decimalplace.)
Wait time days
b. What is the process time? (Round your answer to 2decimal places.)
Process time days
c. What is the inspection time? (Round your answer to 2decimal places.)
Inspection time days
Waltner Corporation's management reports that its averagedelivery cycle time is 20.0 days, its average throughput time is13.5 days, its manufacturing cycle efficiency (MCE) is 0.44, itsaverage move time is 0.2 day, and its average queue time is 4.0days. |
Required: | |
a. | What is the wait time? (Round your answer to 1 decimalplace.) |
Wait time | days |
b. | What is the process time? (Round your answer to 2decimal places.) |
Process time | days |
c. | What is the inspection time? (Round your answer to 2decimal places.) |
Inspection time | days |