Riggs Corp. management is planning to spend $650,000 on a new marketing campaign. They believe that this action will result in additional cash flows of $285,000 over the next three years. If the discount rate is 17.5 percent, what is the NPV on this project? (Enter negative amounts using negative sign e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final answer to 0 decimal places, e.g. 1,525.)
Riggs Corp. management is planning to spend $650,000 on a new marketing campaign. They believe that this action will result in additional cash flows of $285,000 over the next three years. If the discount rate is 17.5 percent, what is the NPV on this project? (Enter negative amounts using negative sign e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final answer to 0 decimal places, e.g. 1,525.)