Umanzor Corporation uses activity-based costing to assignoverhead costs to products. Overhead costs have already beenallocated to the company's three activity cost pools as follows:Processing, $52,100; Supervising, $30,100; and Other, $18,600.Processing costs are assigned to products using machine-hours (MHs)and Supervising costs are assigned to products using the number ofbatches. The costs in the Other activity cost pool are not assignedto products. Activity data appear below:

MHs(Processing) Batches(supervising)
Product S5 17,400 750
Product F5 900 1,030
Total

18,300

1,780

What is the overhead cost assigned to Product S5 underactivity-based costing?