In 2018, the Westgate Construction Company entered into acontract to construct a road for Santa Clara County for$10,000,000. The road was completed in 2020. Information related tothe contract is as follows: 2018 2019 2020 Cost incurred during theyear $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs tocomplete as of year-end 5,810,000 1,826,000 0 Billings during theyear 2,030,000 4,444,000 3,526,000 Cash collections during the year1,815,000 3,900,000 4,285,000 Westgate recognizes revenue over timeaccording to percentage of completion. rev: 09_15_2017_QC_CS-99734Required: 1. Calculate the amount of revenue and gross profit(loss) to be recognized in each of the three years. (Do not roundintermediate calculations. Loss amounts should be indicated with aminus sign.)
In 2018, the Westgate Construction Company entered into acontract to construct a road for Santa Clara County for$10,000,000. The road was completed in 2020. Information related tothe contract is as follows: 2018 2019 2020 Cost incurred during theyear $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs tocomplete as of year-end 5,810,000 1,826,000 0 Billings during theyear 2,030,000 4,444,000 3,526,000 Cash collections during the year1,815,000 3,900,000 4,285,000 Westgate recognizes revenue over timeaccording to percentage of completion. rev: 09_15_2017_QC_CS-99734Required: 1. Calculate the amount of revenue and gross profit(loss) to be recognized in each of the three years. (Do not roundintermediate calculations. Loss amounts should be indicated with aminus sign.)