Computation of Variances and Other MissingData
The following data for O'Keefe Company pertain to the production of500 units of Product X during December. Selected data items areomitted. Fill in the missing amounts.
Direct materials (all materials purchased were used duringperiod) Standard cost per unit: Answer pounds at 2.88 per pound Total actual cost: Answer pounds costing $5,673 Standard cost allowed for units produced: $5,760 Materials price variance: $Answer AnswerFU Materials quantity variance: $144 U Direct labor Standard cost: 2 hours at $7.00 Actual cost per hour: $7.25 Total actual cost: $Answer Labor rate variance: $Answer AnswerFU Labor efficiency variance: $140 U Variable overhead Standard costs: Answer hours at $4.00 per direct laborhour Actual cost: $3,700 Variable overhead spending variance: $Answer AnswerFU Variable overhead efficiency variance: $Answer AnswerFU
Please answer all parts of the question.
Computation of Variances and Other MissingData
The following data for O'Keefe Company pertain to the production of500 units of Product X during December. Selected data items areomitted. Fill in the missing amounts.
Direct materials (all materials purchased were used duringperiod) |
Standard cost per unit: Answer pounds at 2.88 per pound |
Total actual cost: Answer pounds costing $5,673 |
Standard cost allowed for units produced: $5,760 |
Materials price variance: $Answer AnswerFU |
Materials quantity variance: $144 U |
Direct labor |
Standard cost: 2 hours at $7.00 |
Actual cost per hour: $7.25 |
Total actual cost: $Answer |
Labor rate variance: $Answer AnswerFU |
Labor efficiency variance: $140 U |
Variable overhead |
Standard costs: Answer hours at $4.00 per direct laborhour |
Actual cost: $3,700 |
Variable overhead spending variance: $Answer AnswerFU |
Variable overhead efficiency variance: $Answer AnswerFU |
Please answer all parts of the question.