GMS 450 Lecture Notes - Lecture 8: Critical Path Method, Project Manager, Project A

178 views6 pages
GMS450
Chapter 8: Resource Allocation (5 math questions from project crashing)
Expediting a Project
Coside a idge ostutio pojet.
Digging the drainage ditch takes 10 days with a team of 3 workers.
There are 3 other workers that can be added if the stop thei o task oete pouig.
The i.e.,  okes a oplete diggig i  das at the ost of delaig the task oete pouig
The PM can also rent an excavator machine to get the job done in 2 days
What is the key trade off in making the decision?
Should consider factors of adverse consequences (compare both)
For option 1) if it defects, the completion time of the project, it may affect the adverse way (can find this using slack time)
Project Crashing
Project Crashing: Shortening (or expediting) some activities within a project to reduce overall project completion time (the one on
the critical path should be crashed b/c want to shorten the time of critical path)
Project Costs
- Direct Costs: Labor, materials, and any other costs directly related to activities (direct costs will increase if you want to
shorten the completion time of the project. i.e. hire more people, rent more equipment)
- Indirect Costs: Administration, depreciation, financial, and other overhead costs that can be avoided by reducing total
project time
- Penalty Costs: If project extends beyond some specific date (incentives)
Cost to Crash
Normal time (NT): time necessary to complete an activity under normal conditions
Normal cost (NC): activity cost associated with the normal time
Crash time (CT): shortest possible time to complete an activity
Crash cost (CC): activity cost associated with the crash
find more resources at oneclass.com
find more resources at oneclass.com
Unlock document

This preview shows pages 1-2 of the document.
Unlock all 6 pages and 3 million more documents.

Already have an account? Log in
What Activities to Crash? The cheapest one (the one with least cost to crash per period)
Algorithm fo the ea, go though the ash ties oe  oe / if it hages, it’ll ess up the hole uestio
Which activities and for how long should be crashed?
Determining the Minimum Cost Schedule
1. Determine pojet’s itial paths
2. Find the activity or activities on the critical path(s) with the lowest cost of crashing per unit of time
3. Redue the tie fo this atiit util…
a) It cannot be further reduced or
b) Until another path becomes critical, or
c) The increase in direct costs exceeds the savings that results from shortening the project
4. Repeat this procedure until the increase in direct costs is larger than the savings generated by shortening the project
Analyzing Cost Time Trade Offs (hospital example)
Project completion time was 69 weeks (Critical Path Analysis)
Suppose that project indirect costs are $8000 per week
After 65 weeks, the Regional Hospital Board imposes cost of $20k per week if the hospital is not fully operational
Question: what is the saving per week shortening the project?
- Saving per week (up to 65 weeks = 28000)
- Saving per week (beyond week 65 = 8000)
Analyzing Cost Time Trade Offs (Hospital example)
Determine the minimum cost schedule for the hospital project
Project completion time = 69 weeks
Project cost = =$2,624,000
Direct = $1,992,000
Indirect = 69 (8000) = $552,000
Penalty = (69-65) (20,000) = $80,000
find more resources at oneclass.com
find more resources at oneclass.com
Unlock document

This preview shows pages 1-2 of the document.
Unlock all 6 pages and 3 million more documents.

Already have an account? Log in

Get access

Grade+
$40 USD/m
Billed monthly
Grade+
Homework Help
Study Guides
Textbook Solutions
Class Notes
Textbook Notes
Booster Class
10 Verified Answers
Class+
$30 USD/m
Billed monthly
Class+
Homework Help
Study Guides
Textbook Solutions
Class Notes
Textbook Notes
Booster Class
7 Verified Answers

Related Documents